| Future Projects : Pushkar’s Anantha |
|
|
| |
| Level |
|
Payment Percentage |
| While booking |
: |
15% |
| When Foundation work is commenced |
: |
15% |
| On completion of Ground/Stilt Floor Roof slabs |
: |
15% |
| On completion of First Floor Roof slabs |
: |
10% |
| On completion of Second Floor Roof slabs |
: |
10% |
| On completion of Third Floor Roof Slabs |
: |
10% |
| On completion of Fourth Floor Roof Slabs |
: |
10% |
| On Completion of Brickwork in respective Flats |
: |
10% |
| On Handing over |
: |
5% |
|
|
| |
|